C.P. Systems will be working in various locations within the City of North Bay installing sacrificial anodes and test stations on existing metallic water mains to minimize the corrosion of the existing pipelines.
C.P. Systems will be completing localized traffic control in the areas of their work that may result in short delays. A tentative schedule of their work is as follows:
Date |
Street |
From |
To |
August 21 |
Seymour Street |
Venture Cres |
Wallace Rd |
August 22 |
Cholette Street |
Patton St |
Hwy 11 |
August 22 |
Regina Street |
York St |
Ellis St |
August 23 |
Chippewa Street |
Ferguson St |
Fraser St |
August 24 |
Chippewa Street |
Fraser St |
Cassells St |
August 24 |
Oak Street |
John St |
63m North |
August 25 |
Oak Street |
Fisher St |
80m South of Regina St |