Skip to content

Rehabilitation of Lee's Road underway

Traffic will be reduced to one lane using temporary traffic control lights and delays should be expected

The much-awaited Lee's Road rehabilitation starts tomorrow.

The project, which is scheduled for completion by Nov. 11, includes:

  • upgrades to the safety cable guide rail along the length of the adjacent creek;
  • removal of frost heaves;
  • replacement of corroding culverts;
  • pulverizing of existing asphalt road;
  • two lifts of asphalt paving;
  • installation of asphalt curb; ditching and other ancillary items.

Work will occur Monday to Friday between 7 a.m. and 7 p.m. Traffic will be reduced to one lane using temporary traffic control lights and/or flagging personnel and delays should be expected.

The ONR rail crossing on Lees Road is not part of the project and will be upgraded during a separate project. Local access will be maintained throughout the duration of the project says a news release from the City.