City updates road construction

"The resurfacing contract is based on the actual tonnage of asphalt used so after the tender prices have come in we estimate we how many roads we are able to resurface based on the unit prices."
2015 9 22 Ferguson st at Victoria turl
Ferguson Street at Victoria looking west to Memorial Gardens. File photo.

Ferguson Phase 2

·  Traffic signal pole footings were installed at the end of last week – installation of ducts for the traffic signal wiring will be undertaken this week

·  Curbs installation at the Worthington intersection are expected later in the week

·  Road prep for paving will continue – work will continue to install the top granular for the road base – paving is expect to commence next week

·  Worthington intersection will be temporarily open for the Thanksgiving weekend, but will close again next week to continue with the work at the intersection

Ferguson Phase 3

·  Contractor will work on commissioning the watermain and videoing sewer pipes

John St. Bridge

·  Contractor will work on installing rebar for the bridge deck

·  Contractor expected to pour bridge deck later in the week, pending cooperative weather

Pinewood Park Drive Sanitary Sewer

·  The main line sewer was completed last week – Contractor will continue with the remaining sewer laterals

·  Contractor performing work to confirm condition of sewer installed on previous contract

Cedar Heights Watermain

·  Contractor adjusting catchbasins to final grade so that curb can be completed around catchbasins

·  Contractor continuing with asphalt removal & road grading for paving prep between the Hospital entrance and Monastery Rd – paving expected to start later in the week

·  Contractor continuing with work on sanitary sewer and watermain between the north and south school entrances

Cedar Heights Booster Pumping Station

·  Contractor will start installation of remaining exterior siding, soffit/fascia and veneer

·  Contractor will prep and grade the site area for lawn areas, driveway, and parking area 

Merlin

·   The non-shrink grouting of the bored main will happen today.

Eva

·  Our crew completed the final Tie today and is backfilling excavation.  A catchbasin will be replaced at the corner of Kehoe and Eva prior to Pipe work completion. Asphalt restoration is being scheduled asap.

Resurfacing

·  The resurfacing contract is based on the actual tonnage of asphalt used so after the tender prices have come in we estimate we how many roads we are able to resurface based on the unit prices. This year we have completed the roads we were expecting to finish and we underestimated by approximately $300,000 (i.e. needed less material do to the repairs required). In order to complete the program we are bringing the contractor back to resurface the following roads that would have been on next year’s list: Ski Club from 719 Ski Club to little bit pass Chapais; Lakeshore Drive from Premier to 40 m west of Ferris. These last two repairs are expected to be completed within the next couple of weeks.